Tuesday, April 15, 2008
Our grade beams for our foundation are being handled in 5 phases. We began the at the beginning of April, and they will be dug and poured over a 7-8 week period. This photo shows the steel that was engineered for the beams. We are building under the same seismographic standards as southern California.
Wednesday, April 2, 2008

This is a photo of the crane that we brought in to drill our auger pilings. We used this method, as opposed to driving the pilings, so that it would be quieter and have less vibration. We drilled 323 pilings at an average of 50 feet deep to pass the load of the building to the rock below. Berkel, the contractor who did the drilling, finished up in late March.

In January of 2008 we installed our underground storm water retention system. This system is to capture the first inch of rain and holding it for 48 hours. This will help the city storm drains from flooding over, and allows us to settle out 90% of the solid particles before they would go out into King's Creek.


